CONSTRUCTION OF TRAFFIC AREAS WITH ACCOMPANYING INFRASTRUCTURE AT THE MIŠELUK III LOCATION - PHASE 1
01.03.2025.

Work is underway on the construction of traffic areas with accompanying infrastructure at the Mišeluk III - Phase 1 site.
The work began on February 13, 2023, with a completion date of 910 calendar days.
This investment includes the construction of a water supply network (5,399.61 m), storm sewers (3,784.69 m), sewage systems (3,718.78 m), traffic surfaces (3,791 m), 65 parking spaces, pedestrian paths (3,747 m), bicycle paths (3,119.60 m3), 196 public lighting poles, the installation of benches (177 pieces), waste bins (129 pieces), bicycle racks (6 pieces), as well as horticultural landscaping (10,028 m2).
The value of the investment is 1,281,908,817.36 dinars (including VAT).